As the Sysdig-Prod license is approaching time of expiration, we will need to apply the new license to continue to utilise the service.

This necessitates a very brief service interruption, as per the Sysdig documentation we require to restart some of the Sysdig Backend Components (however these are controlled by multi-replica deployments w/ failover, so impact should be minimal)

Given the short time-frame until expiration, this will be put forward as an Emergency Change (as there is less than 1/2 weeks to give notice)
Posted Apr 05, 2024 - 16:34 BST
Update
As the Sysdig-Prod license is approaching time of expiration, we will need to apply the new license to continue to utilise the service.

This necessitates a very brief service interruption, as per the Sysdig documentation we require to restart some of the Sysdig Backend Components (however these are controlled by multi-replica deployments w/ failover, so impact should be minimal)

Given the short time-frame until expiration, this will be put forward as an Emergency Change (as there is less than 1/2 weeks to give notice)
Posted Apr 05, 2024 - 16:33 BST
In progress
As the Sysdig-Prod license is approaching time of expiration, we will need to apply the new license to continue to utilise the service.

This necessitates a very brief service interruption, as per the Sysdig documentation we require to restart some of the Sysdig Backend Components (however these are controlled by multi-replica deployments w/ failover, so impact should be minimal)

Given the short time-frame until expiration, this will be put forward as an Emergency Change (as there is less than 1/2 weeks to give notice)
Posted Apr 05, 2024 - 16:01 BST
Scheduled
As the Sysdig-Prod license is approaching time of expiration, we will need to apply the new license to continue to utilise the service.

This necessitates a very brief service interruption, as per the Sysdig documentation we require to restart some of the Sysdig Backend Components (however these are controlled by multi-replica deployments w/ failover, so impact should be minimal)

Given the short time-frame until expiration, this will be put forward as an Emergency Change (as there is less than 1/2 weeks to give notice)
Posted Apr 03, 2024 - 17:18 BST